Project Progress
The Community Hub project is now entering a very exciting phase with work on significant parts of the project taking place. The Community Hub team will be issuing updates as work on St Leonard's and its surroundings starts and progresses. Check this page regularly for new information.
Monday 4th August 2025
On Monday 4th August 2025 contractors will be in the churchyard digging the trench to lay ducting which will eventually bring the water, electric and phone lines in and the sewerage out of the building. This work will take approximately 2 to 3 days and although the road will NOT be closed there will be the contractors’ vehicles parked down by the church, Rectory Lane/High Street but there will still be access available to and from Rectory Lane.
Click here to read the full Village Hub update document: